Thursday, August 1, 2013 Reconstruction of roadway, utility upgrades, and replacement of trunk water mains on Broadway between Rector and Ann Streets is scheduled to begin on or about Monday, August 5th. The work will be conducted in two-block segments at a time. 1st Segment (August 2013 - December 2013): Rector – Thames (West Side) 2nd Segment (December 2013 - July 2014): Thames – Liberty (West Side) The remaining segments are to be determined/scheduled as…